Paving the parking area at Central Material Laboratory

This project involves paving the courtyard for the Central Materials, with M/s. Multiplex as the contractor. The JMM Team learnt that this contract had two (2) assignments, i.e.

  • Upgrading of access road to Busoga College Mwiri in Jinja; and
  • Paving the Central Materials Laboratory courtyard.

Project Details

Information

Project Name:

Paving the courtyard for the Central Materials Laboratory

Funding Agency:

Government of Uganda

Contractor:

M/s. Multiplex

Implementing Agency::

Ministry of Works and Transport

Contract duration:

9 Months

Contract sum:

UGX.4.414 Bn

Commencement date:

August 2018

Expected completion date:

May 2019, and not yet revised